'Highway blocked, stones pelted, cops injured': BJP faces open revolt in Madhya Pradesh over Narottam Mishra ticket snub | Two Kolkata Police DCPs suspended over alleged remarks against Bengal CM Suvendu Adhikari | Bail to Bloodbath: Telangana man allegedly kills wife, kids and teen who accused him of sexual harassment | Prakash Raj gets bail in multiple voter registration case linked to 2019 polls | ED raids Shekhar Suman associate's premises in FEMA case; phone allegedly thrown from 13th floor | 'Candidate fled': Prashant Kishor jibes BJP over Bankipur nominee change | BJP replaces candidate days before high-stakes Bankipur bypoll | Foreign franchise league enters India! BBL opener to be played in Chennai, announce Modi-Albanese | 'They could have stopped me': Vijay blames police, former DMK government over Karur stampede | 'People will correct their 2025 mistake': Electoral debutant Prashant Kishor predicts BJP defeat in Bankipur

Centre is all set to start stalled works of 2000 MW Subansiri Lower Hydro project

| | Feb 13, 2017, at 09:35 pm
Guwahati, Feb 13 (IBNS): The Centre is all set to start the construction works of the stalled 2000 MW Subansiri Lower Hydro Electric Project.

A top official of the Union Power Ministry said that, the Centre is targeting to complete the works of the project by mid of 2018.

Arunachal Pradesh Chief Minister Pema Khandu on Sunday said the the Arunachal Pradesh government will sort out all the problems on implementation of the stalled hydro electric project soon.

Khandu said that, he would hold talks with the Centre and his Assam counterpart Sarbananda Sonowal into the matter for an early sorting out the issue.

Khandu and his cabinet colleagues had inspected the construction site of the hydro electric project and assured to the National Hydroelectric Power Corporation (NHPC) officials to sort out the problems for halted construction works soon.

Khandu said that, the state government losing around Rs 1.20 crore per day, which could have been accured from the 12% free power share.

Meanwhile, the top official of the Union Power Ministry said that, the stalled works of the hydro electric project will be started soon.

The construction work of the hydro electric project has been stalled since December 2011 following amid protests by anti-dam groups from Assam including Krishak Mukti Sangram Samittee (KMSS), All Assam Students Union (AASU), Asom Jatiyatabadi Yuba Chatra Parishad (AJYCP).

The anti-dam groups alleged that, the people residing in the downstream will be affected, if is any breach in the project.

The initial cost of the project was estimated at Rs 6285 crore when construction begun in 2005, and now the revised cost estimate has escalated to Rs 17,435 crore, due to delay.

On the other hand, the NHPC official said that, around 55% construction works have been completed till date.


(Reporting by Hemanta Kumar Nath)

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm