Bengal CM Suvendu Adhikari backs move to stop entry to Bankra Mosque inside Kolkata airport operational area | Big win for Vijay government! Supreme Court stays Madras HC's cow slaughter ban in Tamil Nadu | Badrinath Temple donation theft case: Key accused Pramod Nautiyal arrested in major breakthrough | 'Citizenship must be decided fairly': Supreme Court quashes Gauhati HC order declaring 27 as foreigners | 'Highway blocked, stones pelted, cops injured': BJP faces open revolt in Madhya Pradesh over Narottam Mishra ticket snub | Two Kolkata Police DCPs suspended over alleged remarks against Bengal CM Suvendu Adhikari | Bail to Bloodbath: Telangana man allegedly kills wife, kids and teen who accused him of sexual harassment | Prakash Raj gets bail in multiple voter registration case linked to 2019 polls | ED raids Shekhar Suman associate's premises in FEMA case; phone allegedly thrown from 13th floor | 'Candidate fled': Prashant Kishor jibes BJP over Bankipur nominee change
NTPC

NTPC’s oldest unit at Singrauli records highest PLF so far in current fiscal

| @indiablooms | Jan 11, 2021, at 10:33 pm

New Delhi: NTPC Ltd’s very first unit, which was commissioned 38 years ago at Singrauli in Uttar Pradesh, has achieved the highest Plant Load Factor (PLF) of 100.24 percent among all thermal units in the country between April 2020 to December 2020, data published by Central Electricity Authority (CEA) showed.

The 200 MW unit was commissioned in 1982 and the robust PLF signifies the exceptional operational and maintenance efficiency at India’s largest power generation company.

Besides the exceptional feat achieved by unit#1, three more NTPC units - Singrauli unit#4 and Korba unit #1 & #2 in Chhattisgarh, have figured among Top 5 performing units.

Further, NTPC Group achieved highest gross generation of 222.4 Billion Unit (BU) from April to December 2020, an increase of 3.8 percent compared to the same period last year. Concurrently, NTPC coal power stations have maintained high availability of 92.21 percent from April 2020 to December 2020 as against 87.64 percent during the same period last year.

Six flagship power plants of NTPC i.e. NTPC Korba (2600 MW) & NTPC Sipat (2980 MW) in Chhattisgarh, NTPC Rihand (3000 MW) in Uttar Pradesh, NTPC Vindhyachal (4760 MW) in Madhya Pradesh, NTPC Talcher Thermal (460 MW) and NTPC Talcher Kaniha (3000 MW) in Odisha have also featured among the top 10 performing thermal plants in the country.

With a total installed capacity of 62.9 GW, NTPC Group has 71 Power stations comprising of 24 Coal, 7 combined cycle Gas/Liquid Fuel, 1 Hydro, 14 Renewables along with 25 Subsidiary & JV Power Stations. The group has over 20 GW of capacity under construction, including 5 GW of renewable/hydro energy projects.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm