Foreign franchise league enters India! BBL opener to be played in Chennai, announce Modi-Albanese | 'They could have stopped me': Vijay blames police, former DMK government over Karur stampede | 'People will correct their 2025 mistake': Electoral debutant Prashant Kishor predicts BJP defeat in Bankipur | New assassination plot against Trump? Israel's secret intelligence raises alarm amid escalating Middle East tension | Ayatollah Ali Khamenei buried at Iran's holiest shrine as Middle East crisis deepens | Indian techie allegedly kills wife in US, sends photo of her body to 'secret girlfriend' in India; arrested | 'I fled the city': Thane doctor quits after alleged assault by Shiv Sena leader | Sensex surges 500 points before losing steam, ends marginally higher after volatile trading session | US court drops charges against Indian-origin doctor who drove Tesla off 250-foot cliff with family | Dalal Street bleeds! Sensex tanks over 1,600 points after Trump declares Iran ceasefire 'over'

Number of delayed infrastructure projects increase to 830

| @indiablooms | Sep 21, 2023, at 08:13 am

New Delhi: The number of delayed infrastructure projects valued at Rs 150 crore and higher in India has increased to 830 as of September 1, 2023, from 809 recorded on August 1, 2023, as per the August 2023 report from the Infrastructure and Project Monitoring Division (IPMD).

Out of the 1,762 projects under scrutiny, 830 are experiencing delays, 550 are progressing on the set schedule, and 43 projects are ahead of schedule.

The remaining 339 projects lack reported commissioning years or tentative gestation periods.

On average, these 830 delayed projects have an overrun of 36.96 months.

Within the delayed projects, 167 have reported additional delays compared to the previous month's completion date, with 59 being high-value mega projects worth Rs 1,000 crore or more.

Furthermore, among the 830 delayed projects, 194 have reported delays ranging from 1-12 months, 190 are facing delays between 13-24 months, 323 are experiencing delays spanning 35-60 months, and the remaining 123 are encountering delays exceeding 60 months.

The total cost overrun for the 1,762 infrastructure projects amounts to Rs 4,77,280.69 crore, which is 19 percent of the total cost.

"Total original cost of implementation of the 1,762 projects was Rs 25,01,400.62 crore and their anticipated completion cost is likely to be Rs 29,78,681.31 crore," the report said.

As of September 1, 2023, a total of Rs 15,57,188.10 crore has been expended on these 1,762 infrastructure projects, the report noted.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm