9 civilians die as suicide bombers crash 2 explosive-laden cars into Pakistani army compound | Hyderabad techie dies by suicide after 6 months of wedding, family alleges dowry harrasment by husband | India defeat Australia by 4 wickets to book a spot in Champions Trophy finals | Maharashtra minister resigns amid outrage over sarpanch's brutal murder in Beed | Haryana Congress worker murder: Video emerges showing accused dragging suitcase with Himani Narwal's body inside it | Supreme Court slams 'oversmart' Samay Raina for making fun of proceedings in Canada, asks him to 'behave' | Indian woman facing death row in UAE for killing a child has been executed: Foreign ministry tells court | Crucial to have Trump’s support, says Zelenskyy a day after fiery White House exchange | 'We're looking for peace, Zelenskyy wants Russia-Ukraine war to continue': Donald Trump after White House public spat | Volodymyr Zelenskyy refuses to apologise to Donald Trump after public spat over Russia-Ukraine war
CPEC
Image: Pixabay

Chinese firm concerned over delay in launch of CPEC solar project in Pakistan

| @indiablooms | Oct 09, 2021, at 08:46 pm

Lahore: A Chinese state company has voiced its concerns over the inordinate delay in the launch and completion of the remaining 600-megawatt portion of the 900MW mega solar power project under the China-Pakistan Economic Corridor (CPEC) amid alleged issues related to the National Electric Power Regulatory Authority (Nepra) and the National Transmission and Despatch Company (NTDC), media reports said.

The firm, in its various communications to the CPEC Authority, Punjab government, Ministry of Energy (power division) and other authorities concerned, has sought immediate resolution of all issues enabling it to launch and complete the remaining part of the Quaid-i-Azam Solar Park in Bahawalpur, Dawn News reported.

“For the last couple of years, the Chinese company, which completed and commissioned 300MW of the 900MW project in 2016-17, has not worked further due to various official bottlenecks. The company has been running after government departments for this clean power generation project for the last couple of years, but to no avail,” explains an official source to Dawn News.

He claimed the remaining 600MW had not yet reached fruition because the issues related to tariff and interconnection study reports were yet to be resolved by Nepra and NTDC.

“Moreover, our re-affirmation of Grid Interconnection Study (GIS) and extension of IEE/NOC approvals and generation licences applications are pending with the NTDC (power planning wing), Nepra and Punjab Environment Protection Department,” the official added citing contents of a recent letter the company wrote to the quarters concerned.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.