RG Kar: Kolkata top cop Vineet Goyal, senior health officials removed, says Mamata after meeting with junior doctors | India raises objections to Iranian supreme leader's minorities remark, says 'look at your own record' | Those filled with hate are defaming India: PM Modi amid row over Rahul Gandhi's Sikh remark in US | RG Kar: Mamata Banerjee, protesting junior doctors hold talks to end impasse | Gujarat's Bhuj-Ahmedabad 'Vande Metro' renamed as 'Namo Bharat Rapid Rail', to be flagged off by PM Modi today
Power Minister R. K. Singh reviews progress and safety aspects of 2000 MW Subansiri Lower Hydroelectric project
Subansiri Project
Image Credit: PIB

Power Minister R. K. Singh reviews progress and safety aspects of 2000 MW Subansiri Lower Hydroelectric project

| @indiablooms | 01 Jun 2023, 02:03 pm

New Delhi: Power minister R. K. Singh on Wednesday discussed the status of the Subansiri Lower Hydroelectric Project, a 2000 Mega Watts undertaking to span across Arunachal Pradesh and Assam, being managed by NHPC Ltd.

The power minister reviewed the construction progress, safety aspects related to the project, and preparedness required to be undertaken in view of the upcoming monsoon season.

The head of the Project presented the current status of the progress achieved in various work packages along with the detailing of safety considerations, and its preparedness as per laid down technical standards in view of the ensuing monsoon months.

The project has achieved significant progress in dam concreting (14 blocks achieved the top level of 210 meters and balance 2 blocks to be completed by June 2023), 37 meters of dam height has been raised with the concrete pouring of more than 2.5 lakhs cubic meters during last 06 months which is a remarkable feat.

Further, the river-facing wall of the powerhouse has been raised up to a safe elevation of 116m and the tail race channel has been completed for all units. the water conductor system is almost ready now.

After the review, the Union Minister expressed satisfaction over the work progress and directed NHPC to move ahead with all necessary safety precautions.

CMD NHPC assured that the company is striving to commission the first unit with 250 MW capacity in coming December or January 2024.

The meeting was attended by Secretary (Power) MoP along with other senior officers from the Ministry, Central Electricity Authority and NHPC.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.