Covid-19: Nearly 7,000 infections in 1 day, tally jumps past 1.38 lakh | No resumption of passenger flight operation in Maharashtra now: Uddhav Thackeray | BJP-TMC faceoff as Dilip Ghosh en-route to his constituency stopped by police | Bengal Guv urges people to remain calm, asks govt to act fast in restoring services | With four new positive cases Assam COVID-19 cases surge to 350 |

Power Ministry eases the process of getting electricity connection

India Blooms News Service | 14 Jul 2016, 08:16 pm
New Delhi, Jul 14 (IBNS): The Union Ministry of Power said on Thursday that it has undertaken several reforms to ease the process of getting electricity, in the past two years.
The central government has made it mandatory to provide electricity connection within fifteen days to the consumers in normal conditions. 
 
A simplified procedure for getting electricity connection has been adopted after detailed discussions with Delhi and Maharashtra Discoms and other concerned agencies, the ministry said.
 
DERC has made the necessary changes to allow LT connection up to 150 KVA and had also rationalized the tariff for the same in 2015. 
 
Ministry has also stipulated the time for each step required for providing the connection. Within three days of online form submission for electricity connection, the field inspection of the site will be done, which will lead to the process to estimate preparation, load sanction and intimation for fee deposit to be completed in next four days. After this, installation work including meter and flow of electricity will be done in eight days, thus completing the whole process in 15 days
 
While applying for connection, consumers in Delhi and Mumbai will be required to provide the self certification for type of consumer along with ID proof and premises ownership. 
 
An amendment to CEA notification have been made to waive off electrical approval for 11 KV installation carried out by Discoms and allowing self certification by Discoms engineers in such cases. 
 
It has been agreed by the Discoms that reliability of power supply will be improved progressively each year till international benchmarks are achieved. 
 
An amendment in CEA notification for allowing installation of transformers up to 500 KVA on double pole structure has also been made, the ministry said. 
 
Apart from these initiatives, a simplified online mechanism for Right of Way (RoW) approval process for electrical works is also under process. 
 
These measures will drastically reduced the time taken for getting an electricity connection and will benefited citizens and industry alike, according to the ministry. 