December 15, 2024 03:28 (IST)
Follow us:
facebook-white sharing button
twitter-white sharing button
instagram-white sharing button
youtube-white sharing button
Pushpa 2 stampede: Allu Arjun walks out of jail, actor's lawyer slams delay in release | Donald Trump intends to end 'inconvenient' and 'very costly' Daylight Saving Time | Suchir Balaji: Indian-origin former OpenAI researcher found dead at US apartment | Bengaluru techie suicide: Karnataka Police issues summons to wife Nikita, her family members | French President Macron appoints centrist leader Francois Bayrou as new Prime Minister | Congress always prioritised personal interest over Constitution: Rajnath Singh | Jaishankar calls attack on Hindus in Bangladesh 'a source of concern' | Allu Arjun arrested over woman's death in stampede during Pushpa 2 premiere show | RBI receives bomb threat in Russian language, case filed | UP teenager kills mother, lives with body for 5 days
Delhi Metro
Wikimedia Commons

Delhi Metro casts first ever pier of Phase 4 work

| @indiablooms | Jul 26, 2020, at 10:55 pm

New Delhi/UNI: The Delhi Metro Rail Corporation (DMRC) took another important step forward in its Phase 4 construction work, as the first pier of this phase of Metro expansion was cast on the Janakpuri West- RK Ashram Marg Metro corridor, a DMRC spokesperson confirmed on Sunday.

'The pier was cast at Keshopur on the elevated stretch between Keshopur and Mukarba Chowk on Saturday night. This major construction milestone has been achieved, despite severe shortage of manpower and other logistical challenges because of the ongoing pandemic,' he said.

The average height of the piers on this corridor is 10 metres. However, the height of the piers will be 20 metres at Madhuban Chowk (crossing with Line 1) and 25 metres at Haiderpur Badli Mor, where this line will cross Line 2.

At Haiderpur Badli Mor, the rail level is going to be the highest - 28 metres in the history of Delhi Metro. Presently, the highest point is at Dhaula Kuan, where the Line 7 viaduct passes at a height of 23.6 metres. The distance between two piers will be about 28 metres.

Piers, in terms of civil engineering, are vertical load-bearing structures, which act as intermediate support for adjacent ends of two spans.

They form the vertical support structures, on which the elevated Metro viaducts stand. Metro piers today dot innumerable road medians in Delhi, through which elevated Metro corridors run. Pier numbers are now important landmarks for addresses across the NCR.

The 28.92 km long Janakpuri West-R K Ashram Marg corridor is an extension of Magenta Line and will come up with 22 stations. While 21.18 kilometres of this corridor will be elevated, 7.74 kilometres will be underground. Construction work on this particular section had started in December last year.

On July 17, the work on the underground section of this corridor was commenced with the beginning of D Wall construction work at the Krishna Park Extension Metro station. On June 24, DMRC had started the casting work of u-girders, which would be installed on the elevated section of this corridor.

Under Phase Four, 61.679 kilometres of new Metro lines will be constructed across three different corridors, comprising 45 Metro stations.

These new sections will provide inter-connectivity among the already operational sections of Delhi Metro. Out of this, 22.35 kilometres will be underground while rest will be elevated, the spokesperson added.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.