Punjab cop dismissed for facilitating TV interview of Larence Bishnoi while in custody | 'Not Veer Savarkar', Congress student wing demands Delhi college be named after Manmohan Singh | 'Cowardly': PM Modi condemns New Orleans terrorist attack that killed 15 | Prashant Kishor starts fast unto death over Bihar Public Service Commission prelims cancellation demand | Bangladesh court denies bail to arrested Hindu monk Chinmoy Krishna Das | Tesla Cybertruck with fuel and fireworks explodes near Donald Trump's Las Vegas hotel, 1 killed | US: Mass shooting at a New York nightclub, 11 people shot | Truck driver who rammed into New Orleans crowd flying ISIS flag identified as US Army veteran Shamsud-Din Jabbar | SRK, Akshay Kumar praise PM Modi's global initiative to take Indian cinema to a greater scale | Manipur CM N Biren Singh responds after Congress leader asks him 'why can't PM' visit' violence-hit northeastern state
Sunni Dam
Representational Image (Credit: Prateek Srivastava via Unsplash)

Cabinet grants investment approval for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd

| @indiablooms | Jan 05, 2023, at 02:41 am

New Delhi/IBNS: The Cabinet Committee on Economic Affairs (CCAE) Wednesday approved the investment for the 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd.

The estimated cost of the project is Rs. 2614.51 crore including Rs 13.80 crore as budgetary support from the government for the cost of enabling infrastructure.

Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs 246 crore till January 2022.

The project cost includes hard costs amounting to Rs.2246.40 crore, Interest During Construction (IDC), and Financing Charges (FC) of Rs. 358.96 crore and 9.15 crore respectively.

The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer is capped at 10 percent of the sanctioned cost.

The implementation of the project is expected to generate around 4000 direct and indirect employment during the peak construction of the project.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.