In a setback for Donald Trump, US judge orders federal agencies to rehire fired workers: Report | 'We will thwart conspiracies hatched by Centre': Revanth Reddy on delimitation exercise | Chennai doctor, his wife along with two sons die by suicide due to huge debt: Cops | Amid language debate, Tamil Nadu drops rupee symbol in state budget | Scientist killed in assault by neighbour over parking argument in Mohali | British woman tourist raped in Delhi hotel by man she befriended on social media | Gold smuggling case: Court restrains media from publishing, telecasting defamatory statements against Ranya Rao | Trump warns Putin of 'devastating' financial impacts if Russia blocks Ukraine ceasefire | 'People are going to Russia right now as we speak: Donald Trump on Ukraine war ceasefire talks | Pakistani army claims to have freed all hostages in passenger train siege; 28 personnel killed
Sunni Dam
Representational Image (Credit: Prateek Srivastava via Unsplash)

Cabinet grants investment approval for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd

| @indiablooms | Jan 05, 2023, at 02:41 am

New Delhi/IBNS: The Cabinet Committee on Economic Affairs (CCAE) Wednesday approved the investment for the 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd.

The estimated cost of the project is Rs. 2614.51 crore including Rs 13.80 crore as budgetary support from the government for the cost of enabling infrastructure.

Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs 246 crore till January 2022.

The project cost includes hard costs amounting to Rs.2246.40 crore, Interest During Construction (IDC), and Financing Charges (FC) of Rs. 358.96 crore and 9.15 crore respectively.

The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer is capped at 10 percent of the sanctioned cost.

The implementation of the project is expected to generate around 4000 direct and indirect employment during the peak construction of the project.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.