India and Pakistan agreed to stop military actions: Govt confirms Trump's ceasefire claim | India, Pakistan have reached full and immediate ceasefire: Donald Trump announces on Truth Social | 'Frivolous allegation': India dismisses Pakistan's 'Indian missiles hit Afghanistan' disinformation | India opposes IMF's proposal to extend fresh loans to Pakistan, abstains from voting | Fresh Pakistani drones target Jammu, Samba and Pathankot; explosion heard in Pokhran | PM Modi meets all three service chiefs amid escalated tensions with Pakistan | 'We stand in unwavering solidarity with our armed forces': Gautam Adani amid escalation with Pakistan | 'India will firmly counter any escalation': S Jaishankar speaks to US Secretary Marco Rubio after Pakistan drone attack | Breaking News: Blackout in Jammu as Pakistan launches fresh attacks on Jammu, heavy shelling on, sirens heard | Ensure smooth functioning of essential services: Amit Shah tells states in security review meet after Operation Sindoor
Sikkim
Image Credit: PIB

Rail Connectivity to Sikkim on fast-track: Railway Ministry

| @indiablooms | Oct 21, 2022, at 03:31 am

New Delhi: The Sivok-Rangpo rail project to connect Sikkim with the rest of India's rail network is showing perceptible progress with 58 percent of mining work completed in 14 main tunnels- 22.23 km of 38.65 km and 42 percent work completed of 13 major bridges, Ministry of Railways said Wednesday.

North Eastern Region is served by Northeast Frontier Railway consisting of eight states i.e. Assam, Arunachal Pradesh, Nagaland, Manipur, Mizoram, Tripura, Meghalaya and Sikkim.

Out of eight states of the North Eastern Region, rail network connectivity now exists in seven states.

For Sikkim, the new line project Sivok-Rangpo (44 km) was sanctioned. The foundation stone of this project was laid on 30.10.2009 by the then railway minister at Sivok (West Bengal), and at Rangpo (in Sikkim) by the then vice-president of India on the same day.

Out of the total length of 44.96 km, 38.65 km (86%) is in tunnels, 2.24 km (5%) in Bridges and 4.79 km (9%) length in open cutting/filling of station yards.

The proposed line consists of 14 tunnels with the longest tunnel of 5.30 km and the smallest tunnel covering 538 metres.

Five stations including Sivok and Rangpo are planned on the proposed railway line.

Four stations are proposed to be open crossing stations e.g., Sivok, Riyang, Melli & Rangpo, and one underground halt station e.g. Teesta Bazar.

The tunnelling which is about 86% of the total length is constructed by the latest Technique called NATM (New Austrian Tunnelling Method).

The works of this project are supervised by International Consultants so that safety and quality are ensured.

IRCON is taking all the measures so that there is minimum disturbance to the Environment and Forest.                                    

The railway ministry also tweeted a video of the project.

 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Close menu