15 killed, 20 injured as bus plunges into gorge in J&K’s Udhampur | Oil jumps over 5% as Strait of Hormuz closure fuels supply fears | Pushback from smartphone makers: Centre drops Aadhaar app pre-install plan — report | Meta eyes first wave of layoffs on May 20: Report | TCS breaks silence on Nida Khan: ‘No HR role, no power’ in Nashik case | ‘Panic reaction’: Rahul Gandhi on women’s bill, says PM Modi ‘wants to send a message’ | Adani Group shares rise as Gautam Adani becomes Asia’s richest, overtakes Mukesh Ambani | TCS Nashik ‘conversion’ case accused seeks anticipatory bail citing pregnancy | IT raids TMC candidate Debasish Kumar’s premises ahead of Bengal polls | Bengal SIR: Supreme Court allows voters restored by tribunal till April 21 and 27 to vote

Adani Energy Solutions commissions biggest inter-regional 765 KV transmission line across Maharashtra, Telangana, and Andhra Pradesh

| @indiablooms | Oct 19, 2023, at 10:24 pm

Warangal: Adani Energy Solutions Ltd has successfully commissioned the Warora Kurnool Transmission line, covering 1,756 circuit kms across Maharashtra, Telangana, and Andhra Pradesh.

This project is set to fortify the national power grid, enabling a smooth transmission of 4,500 MW of electricity between the western and southern regions.

It will improve the resilience of the southern region's grid and facilitate the extensive integration of power generated from renewable sources.

Warora Kurnool Transmission Limited (WKTL) was established in April 2015 to create an extra inter-regional alternating current link for power transfer into the southern region - Warora-Warangal and Chilakaluripeta-Hyderabad-Kurnool.

This also includes the establishment of a 765/400 kV sub-station in Warangal.

WKTL is the most extensive 765 kV D/C (hexa conductor) project awarded through tariff-based competitive bidding under a single scheme. This covered the installation of a 1,756 circuit km (ckm) transmission line cutting across Maharashtra, Telangana, and Andhra Pradesh, as well as the establishment of a 765 KV sub-station in Warangal, based on a build, own, operate, and maintain framework.

Initially assigned to Essel Infraprojects Ltd in early 2016, the project was later taken over by Adani Energy Solutions Limited (AESL) in March 2021, subsequent to the stressed debt restructuring undertaken by creditors.

The project was exceptionally large-scale, using 103,000 metric tonnes of steel for its towers, equivalent to material for 10 Eiffel Towers.

It also utilized 30,154 km of specialized alloy conductor material for transmission lines, comparable to three moon circumnavigations.

Notably, two 102 m high mid-stream towers were erected on the Krishna River, a feat accomplished within a tight three-month window of low water levels.

The project faced numerous challenges, including crossing 116 major power lines, electrified railways, and national highways.

It navigated disruptions caused by global events like COVID-19 and the Russia-Ukraine war, affecting commodity supply chains and necessitating repeated logistical adjustments.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm