Israel says Hezbollah chief’s nephew-cum-secretary killed in Beirut strikes last night | Modi slams TMC on trade, fisheries at Haldia; vows 7th pay commission for govt employees | ‘US military will remain in and around Iran’: Trump amid fragile ceasefire | BJP eyes Assam hattrick, Puducherry comeback; LDF faces Kerala test | Israel claims Hezbollah chief's nephew killed in Beirut strikes last night | Jaishankar’s high-stakes diplomatic tour: EAM to visit UAE this week, first visit amid Middle East conflict | Passport row: Barricades outside Pawan Khera’s Hyderabad house after Himanta Biswa Sarma's warning | ‘Allow excluded voters to vote’: Mamata slams voter list freeze amid SIR row, to move Supreme Court | US, Iran agree to 2-week ceasefire deal, reopening Strait of Hormuz | ‘Prudent to wait and watch’: RBI keeps repo rate unchanged at 5.25% amid global volatility

L&T wins Rs. 1,885 cr order from NTPC

| | Sep 13, 2014, at 04:21 am
Mumbai, Sept 12 (IBNS): Larsen & Toubro Limited (L&T) through its joint venture company L&T-MHPS Boilers Private Limited (LMB) has secured an order worth Rs. 1,885 crore from NTPC Limited.

The contract includes setting up of two units of 660 MW each supercritical steam generators for Tanda Thermal Power Plant Stage-II on an engineering, procurement and construction (EPC) basis.

LMB’s scope includes design, engineering, supply, construction, erection, testing, commissioning and conducting performance guarantee of two coal-fired steam generator units with supercritical parameters.

The project site is located on the banks of the Tanda canal near Bahadurpur village in the Ambedkar Nagar district of Uttar Pradesh.

This is LMB’s first order for supercritical steam generators from NTPC.

The order was won through competitive bidding involving several national and international players. The project is scheduled to be completed in 46 and 52 months for the respective units.

Commenting on the order, Shailendra Roy, Whole-time Director (Power, Minerals & Metals) L&T said, “We have the manufacturing and execution capabilities to deliver to stringent schedules while conforming to global standards.” The order from NTPC affirms L&T’s credentials in EPC execution of power plant equipment.

LMB is currently executing 11 units of similar large capacity steam generators (660/700 MW) in India totaling 7340 MW.

Two units of Nabha Power Ltd at Rajpura (Punjab) have already achieved commercial operation and the remaining are in advanced stages of execution. LMB also caters to markets in countries like Taiwan, Egypt, Saudi Arabia and the Philippines for engineering services and supply of pressure parts and pulverisers.
 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm