Haryana Congress worker murder: Video emerges showing accused dragging suitcase with Himani Narwal's body inside it | Supreme Court slams 'oversmart' Samay Raina for making fun of proceedings in Canada, asks him to 'behave' | Indian woman facing death row in UAE for killing a child has been executed: Foreign ministry tells court | Crucial to have Trump’s support, says Zelenskyy a day after fiery White House exchange | 'We're looking for peace, Zelenskyy wants Russia-Ukraine war to continue': Donald Trump after White House public spat | Volodymyr Zelenskyy refuses to apologise to Donald Trump after public spat over Russia-Ukraine war | 'Make a deal or we are out': Donald Trump tells Volodymyr Zelenskyy at White House | Himachal govt seeks fund from temple to support welfare schemes, BJP calls move 'shocking' | Injustice to opposition MLAs: Atishi writes to Delhi Assembly Speaker on suspension of 21 AAP lawmakers | We will leave for US tomorrow: Father of Indian student Neelam Shinde after urgent visa grant
Subansiri Project
Image Credit: PIB

Power Minister R. K. Singh reviews progress and safety aspects of 2000 MW Subansiri Lower Hydroelectric project

| @indiablooms | Jun 01, 2023, at 07:33 pm

New Delhi: Power minister R. K. Singh on Wednesday discussed the status of the Subansiri Lower Hydroelectric Project, a 2000 Mega Watts undertaking to span across Arunachal Pradesh and Assam, being managed by NHPC Ltd.

The power minister reviewed the construction progress, safety aspects related to the project, and preparedness required to be undertaken in view of the upcoming monsoon season.

The head of the Project presented the current status of the progress achieved in various work packages along with the detailing of safety considerations, and its preparedness as per laid down technical standards in view of the ensuing monsoon months.

The project has achieved significant progress in dam concreting (14 blocks achieved the top level of 210 meters and balance 2 blocks to be completed by June 2023), 37 meters of dam height has been raised with the concrete pouring of more than 2.5 lakhs cubic meters during last 06 months which is a remarkable feat.

Further, the river-facing wall of the powerhouse has been raised up to a safe elevation of 116m and the tail race channel has been completed for all units. the water conductor system is almost ready now.

After the review, the Union Minister expressed satisfaction over the work progress and directed NHPC to move ahead with all necessary safety precautions.

CMD NHPC assured that the company is striving to commission the first unit with 250 MW capacity in coming December or January 2024.

The meeting was attended by Secretary (Power) MoP along with other senior officers from the Ministry, Central Electricity Authority and NHPC.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm
PM Modi on Budget 2024 Jul 23, 2024, at 09:30 pm