Four killed in fresh Manipur violence as protesters take bodies to Chief Minister’s residence | Tiger Shroff firing: Three accused arrested on train in Rajasthan, suspected Bishnoi gang link emerges | 'Internet access a fundamental right for children': SC rejects age-based 'blanket' ban | 'We will fight our own government': RG Kar victim's father threatens fresh protest after Sandip Ghosh gets bail | RG Kar shocker: Sandip Ghosh gets bail as only 7 of 147 witnesses examined, junior doctor blasts CBI | Trump waives Russia-related sanctions | 'How dare Elon Musk?' Owaisi defends Modi after billionaire's 'real boss' jibe at Ambani | 'B****y S***': IAS officer's abuse of female colleague during virtual J&K meeting sparks row | Aamir Khan’s nephew Imran Khan asked to leave India by Oct 28 after joining anti-CEC protest | ‘Their crime? Demanding justice’: Rahul Gandhi slams 4 AM detention of Ankita Bhandari’s parents
Tata
Tata Power Renewables advancing India's energy transition through its 190.5 MW FDRE project at Kalasar, Bikaner, Rajasthan.Photo: PR Team

Tata Power Renewables marks a major milestone with the commissioning of 190.5 MW FDRE project in Rajasthan. All details inside

| @indiablooms | Aug 24, 2026, at 04:57 pm

Tata Power Renewable Energy Limited (TPREL), one of India's leading renewable energy companies and a subsidiary of The Tata Power Company Limited (Tata Power), has commissioned its 190.5 MW Solar FDRE project at Kalasar, Bikaner, Rajasthan which is under the contractual capacity of 460 MW Firm and Dispatchable Renewable Energy (FDRE) Project.

The 190.5 MW project has been developed under SJVN FDRE Tranche-1. The project will supply energy to HPPC, MSEDCL and NPCL discoms.

The project marks another significant milestone in India's clean energy journey by integrating large-scale solar generation with advanced energy storage and grid support technologies to deliver reliable, dispatchable renewable power.

The project demonstrates TPREL's engineering excellence and execution capabilities, having overcome several complex challenges including compressed project timelines, global supply chain disruptions impacting the availability of transmission line materials, module mounting structures and other critical equipment. It has successfully adopted several new technologies such as BESS, Harmonic Filter Bank and Static Var Generator systems.

Among the project's notable execution milestones was the completion of the switchyard within just three months and the Harmonic Filter Bank within one month, reflecting TPREL's focus on speed, quality and execution excellence.

With this project, TPREL's total renewable utility capacity has reached 12.4 GW. Of this, around 6.9 GW is operational, including 5.6 GW of solar and 1.3 GW of wind capacity, while close to 5.5 GW is under various stages of implementation, are expected to be commissioned in phases over the next 24 months.

The company remains committed to developing innovative clean energy solutions that contribute to India's target of achieving 500 GW of non-fossil fuel capacity by 2030 and Tata Power's vision of a sustainable energy future.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.