Eiffel Tower staff strike after female workers 'sidelined' during Hindu group visit | ‘When will character assassination of women stop?’ Kangana Ranaut amid Udhayanidhi-Trisha row | 11 arms instead of 10! Suvendu Adhikari apologises over Durga image in Bengal govt ad amid Bageshwar Baba row | ‘Meat is core to Shakta Hinduism’: PM Modi adviser hits back at Bageshwar Baba over non-veg ban appeal | ‘No one can dictate what Bengalis eat’: BJP’s blunt message amid Bageshwar Baba’s Durga Puja food row | Delhi hostel collapse: Owner detained after seven die in Satya Niketan tragedy | No Muslims, Aadhaar card and tilak mandatory: VHP lays down rules for Garba, Dandiya in Maharashtra | 'No non-veg near Durga Puja pandals': Bageshwar Baba's big Bengal appeal sparks controversy | 'Law will take its action': Vijay's zero tolerance on insulting women weeks after Udhayanidhi's arrest | Delhi Metro's big warning to content creators: Don't try this viral stunt or face action
Sunni Dam
Representational Image (Credit: Prateek Srivastava via Unsplash)

Cabinet grants investment approval for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd

| @indiablooms | Jan 05, 2023, at 02:41 am

New Delhi/IBNS: The Cabinet Committee on Economic Affairs (CCAE) Wednesday approved the investment for the 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd.

The estimated cost of the project is Rs. 2614.51 crore including Rs 13.80 crore as budgetary support from the government for the cost of enabling infrastructure.

Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs 246 crore till January 2022.

The project cost includes hard costs amounting to Rs.2246.40 crore, Interest During Construction (IDC), and Financing Charges (FC) of Rs. 358.96 crore and 9.15 crore respectively.

The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer is capped at 10 percent of the sanctioned cost.

The implementation of the project is expected to generate around 4000 direct and indirect employment during the peak construction of the project.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.