Married just 17 days ago: Hyderabad engineer mysteriously found dead at US home | ‘We will promote cash’: New UPI charge triggers trader backlash, Opposition protests | Gurugram biker crash: Main accused Kalyan Bainsla sent to police custody for 2 days | ‘Just tax collection’: Ashneer Grover slams new UPI charges above Rs 2,000 | India condemns Houthi attack on Saudi Arabia, warns of threat to Red Sea shipping | Gurugram biker hit by car: Two including main accused arrested after viral road rage video, attempt to murder case filed | Gurugram horror caught on camera: ‘I felt unsafe’—car chases, rams woman biker and flees | BRICS veg menu row: ‘Why shouldn’t we showcase it?’—Harsh Goenka hits back after Rahul Gandhi’s ‘80%’ remark | India-UAE Comprehensive Strategic Partnership in focus: Modi meets Abu Dhabi Crown Prince on BRICS sidelines | Xi Jinping lands in India for BRICS; big Modi meeting set for New Delhi
Jammu Roads

CEO ERA sets deadline for ongoing projects in Jammu  

| @indiablooms | Dec 18, 2020, at 10:21 pm

Srinagar: Chief Executive Officer, Jammu and Kashmir Economic Reconstruction Agency (JKERA) and Jammu TawiFlood Reconstruction Project (JTFRP), Dr. Syed Abid Rasheed Shah, conducted an inspection of ongoingSidhra Surinsar Road sub project being executed by JKERA under the World Bank funded Jhelum TawiFlood Recovery Project.

The Road starts from Sidhra Junction on Jammu-Srinagar Highway and isproposed to be upgraded upto km 19th of Sidhra-Surinsar Road.

The completion of this road will augment the road infrastructure to the tourist circuit of Sidhra-SurinsarMansar. It will also connect the important religious destinations of Utterbehni and Purmandal.During the inspection the CEO passed strict instructions for immediately speeding of the work andcompleting the project in the next 7 months.

Major civil works of road consist of improvement of roadgeometrics and widening of blind curves/black spots.

The CEO directed the engineering staff andcontractor to ensure that quality of the civil works is maintained as per best standards.

Engineering staff gave a detailed presentation to the CEO and apprised that the major component ofaround 60% comprises macadamisation/bituminization which will be done after the first week of March2021.The CEO directed the contractor to immediately increase the manpower and machinery deployed toensure that the project is completed well within time.

On the spot directions were issued to theEngineering staff for strict weekly monitoring of progress.Dr. Abid was accompanied by Nand Kishore Gupta Project Manager, Rajinder Kumar Sharma DeputyProject Manager and other Engineering Staff of JTFRP and consultancies along with the representativesof contractors.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.