Supreme Court slams Bar Council of India over NALSAR row: ‘No power to take action against law students’ | ‘Technical error, not U-turn’: Kerala CM Satheesan denies deleting video slamming cleric’s women remarks after Islamic Scholars’ meet | Bombay HC orders CBI probe into Sushant Singh Rajput's ex-manager Disha Salian's death case | Vijay for PM in 2029? TVK says Rahul Gandhi will ‘hold his hand’ to make him Prime Minister | CJP calls off Sept 5 Delhi march after Supreme Court quashes FIRs against protesters | ‘Dismantle entire terror ecosystem’: Modi’s strong message at SCO Summit in Shehbaz’s presence | Modi’s big appeal after 7.8% GDP growth: ‘Don’t travel abroad, avoid destination weddings’ | Modi-Pezeshkian talks: Iran seeks India’s 'extensive contacts' to end West Asia war | Indus Waters Treaty row: India rejects Hague court order, says ‘no jurisdiction’ over its sovereign decisions | India beats the odds with 7.8% GDP growth; PM Modi has a message for critics
Photo courtesy: Kolkata Metro Facebook page

JICA experts satisfied with progress of Kolkata Metro project at at Bowbazar, Esplanade and Sealdah tunnel

| @indiablooms | Dec 02, 2023, at 07:06 am

Kolkata: A six-member high-level team of Japan International Cooperation Agency (JICA), headed by Saito Mitsunori, on Friday expressed satisfaction with the progress of the metro rail stretch at Bowbazar and the tunnel between Esplanade and Sealdah, a Kolkata Metro Rail Corporation Limited's spokesman said.

Their visit and inspection are part of a review mission and they inspected the works at the Bowbazar and the tunnel between Esplanade and Sealdah, he said.

"After the visit, they had a detailed discussion with KMRCL team headed by MD/KMRCL. JICA expressed satisfaction for the progress, quality and safety standards being followed for the execution of the project," the KMRCL said in a statement.

Kolkata’s Bowbazar area is dotted with several old buildings, some dating back to more than 100 years.

In August 2019, during the construction of the metro tunnel in Bowbazar, Kolkata, there was a significant subsidence that led to damage to several buildings.

The incident occurred due to the impact of the tunnel boring machine on an aquifer, causing water inflow and ground settlement.

The incident resulted in the displacement of residents, damage to structures, and posed challenges for the Kolkata Metro Railway Corporation (KMRC) in addressing the situation.

The incident elicited concerns about safety, rehabilitation, and the impact on the overall metro project.

(With UNI inputs)

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.