Christmas vandalism sparks mass arrests in Raipur; Assam acts too with crackdown on 'religious intolerance' | BJP's VV Rajesh becomes Thiruvananthapuram Mayor after party topples Left's 45-year-rule in city corporation | ‘I can’t bear the pain’: Indian-origin father of three dies after 8-hour hospital wait in Canada hospital | Janhvi Kapoor, Kajal Aggarwal, Jaya Prada slam brutal lynching in Bangladesh, call out ‘selective outrage’ | Tarique Rahman returns to Bangladesh after 17 years | Shocking killing inside AMU campus: teacher shot dead during evening walk | Horror on Karnataka highway: sleeper bus bursts into flames after truck crash, 9 killed | PM Modi attends Christmas service at Delhi church, sends message of love and compassion | Delhi erupts over lynching of Hindu man in Bangladesh; protest outside High Commission | Targeted killing sparks global outrage: American lawmakers condemn mob lynching of Hindu man in Bangladesh

Naidu directs CPWD for early construction of new office complex for Supreme Court

| | Nov 12, 2014, at 12:14 am
New Delhi, Nov 11 (IBNS): Urban Development Minister M.Venkaiah Naidu on Tuesday directed the Central Public Works Department (CPWD) to expedite construction of two additional office complexes for Supreme Court of India.
Expressing concern over the delay in executing the two projects, Naidu directed that revised dates of completion of works should be met without fail. The Minister today inspected the two projects. 
 
Additional office complex, taken up at a cost of Rs.884 cr is coming up opposite the Supreme Court. 
 
Sanctioned in July, 2012 by the Ministry of Law & Justice, this complex was to be completed in three years, but only 14% of the work has so far been completed till now. 
 
With a proposed built up area of 1,80,845 sq.metres, this complex coming in an area of over 12 acres, will be used for offices, storage of records, Library, auditorium/seminar hall, conference halls, Litigants Hall, parking etc. 
 
Under this project, an underground passage to connect existing Supreme Court building and the new complex beneath Mathura Road is also to be built. This complex is to provide parking facility for about 1850 cars. 
 
Naidu directed CPWD to explore the possibility of undertaking works simultaneously in all the six packages. 
 
This complex is now targeted to be completed by September, 2017. 
 
The Minister directed  Praveen Prakash, Joint Secretary(UD) to monitor the progress of the project through regular inspections. 
 
Another additional office building is coming up with in the Supreme Court complex. 
 
This was sanctioned at a cost of Rs.84 cr by the Ministry of Law & Justice in May, 2012 and was scheduled to be completed in December, 2014. 
 
So far, 50% of the work has been completed and the targeted date of completion has been revised to August, 2015. 
 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.