Eiffel Tower staff strike after female workers 'sidelined' during Hindu group visit | ‘When will character assassination of women stop?’ Kangana Ranaut amid Udhayanidhi-Trisha row | 11 arms instead of 10! Suvendu Adhikari apologises over Durga image in Bengal govt ad amid Bageshwar Baba row | ‘Meat is core to Shakta Hinduism’: PM Modi adviser hits back at Bageshwar Baba over non-veg ban appeal | ‘No one can dictate what Bengalis eat’: BJP’s blunt message amid Bageshwar Baba’s Durga Puja food row | Delhi hostel collapse: Owner detained after seven die in Satya Niketan tragedy | No Muslims, Aadhaar card and tilak mandatory: VHP lays down rules for Garba, Dandiya in Maharashtra | 'No non-veg near Durga Puja pandals': Bageshwar Baba's big Bengal appeal sparks controversy | 'Law will take its action': Vijay's zero tolerance on insulting women weeks after Udhayanidhi's arrest | Delhi Metro's big warning to content creators: Don't try this viral stunt or face action
Sikkim
Image Credit: PIB

Rail Connectivity to Sikkim on fast-track: Railway Ministry

| @indiablooms | Oct 21, 2022, at 03:31 am

New Delhi: The Sivok-Rangpo rail project to connect Sikkim with the rest of India's rail network is showing perceptible progress with 58 percent of mining work completed in 14 main tunnels- 22.23 km of 38.65 km and 42 percent work completed of 13 major bridges, Ministry of Railways said Wednesday.

North Eastern Region is served by Northeast Frontier Railway consisting of eight states i.e. Assam, Arunachal Pradesh, Nagaland, Manipur, Mizoram, Tripura, Meghalaya and Sikkim.

Out of eight states of the North Eastern Region, rail network connectivity now exists in seven states.

For Sikkim, the new line project Sivok-Rangpo (44 km) was sanctioned. The foundation stone of this project was laid on 30.10.2009 by the then railway minister at Sivok (West Bengal), and at Rangpo (in Sikkim) by the then vice-president of India on the same day.

Out of the total length of 44.96 km, 38.65 km (86%) is in tunnels, 2.24 km (5%) in Bridges and 4.79 km (9%) length in open cutting/filling of station yards.

The proposed line consists of 14 tunnels with the longest tunnel of 5.30 km and the smallest tunnel covering 538 metres.

Five stations including Sivok and Rangpo are planned on the proposed railway line.

Four stations are proposed to be open crossing stations e.g., Sivok, Riyang, Melli & Rangpo, and one underground halt station e.g. Teesta Bazar.

The tunnelling which is about 86% of the total length is constructed by the latest Technique called NATM (New Austrian Tunnelling Method).

The works of this project are supervised by International Consultants so that safety and quality are ensured.

IRCON is taking all the measures so that there is minimum disturbance to the Environment and Forest.                                    

The railway ministry also tweeted a video of the project.

 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.