Owaisi, Chandrashekhar Azad join hands to challenge BJP in 2027 UP elections | Bihar shocker: Gang-rape survivor thrown off building roof in fresh attack | J&K horror: Two missing SPOs found dead with bullet wounds in Kishtwar | Two missing SPOs found dead with bullet wounds in J&K's Kishtwar | Owaisi, Chandrashekhar Azad join hands to challenge BJP in 2027 UP polls | At least 3 CRPF personnel injured as terrorists open fire on security forces in Jammu and Kashmir's Kulgam | Hijack threat on Air India flight sparks security alert at Kolkata airport before take-off | TMC Canning Paschim MLA Paresh Ram Das arrested at Kolkata airport in rape, extortion cases | Megaspeed breaks silence on Nvidia CEO Jensen Huang row, denies illegal China chip transfers | Nvidia CEO Jensen Huang admits extramarital affair amid shocking Chinese spy allegation
Kolkata Metro
TBM ‘Durga’ completes key tunnel drive in Joka-Esplanade corridor. Photo: PIB/Wikimedia Commons

Kolkata Metro breakthrough: TBM ‘Durga’ completes key tunnel drive, brings Joka-Esplanade corridor closer to reality

| @indiablooms | Jul 10, 2026, at 06:56 pm

The Ministry of Railways on Friday announced a significant milestone for the Kolkata Metro, with Tunnel Boring Machine (TBM) ‘Durga’ successfully achieving a breakthrough on the Purple Line of the Joka-Esplanade Metro Corridor.

The breakthrough marks the completion of one of the underground tunnel drives between Khidderpore and Victoria, bringing the city’s ambitious metro expansion project a step closer to completion.

"The breakthrough achieved today is a key step towards strengthening Kolkata’s urban mass transit network and advancing one of the city’s most important Metro expansion projects," the Ministry said in a statement.

Key Highlights:

  • TBM ‘Durga’ successfully completed its tunnelling operation at Victoria Metro Station.
  • The breakthrough marks the completion of the Khidderpore-Victoria underground tunnel stretch, with tunnelling work having started on July 10, 2025.
  • The achievement reflects engineering excellence, precision planning and effective coordination among various stakeholders.
  • The tunnelling work was carried out while maintaining strict safety and quality standards, with minimal disruption to surface traffic.

The Joka-Esplanade Metro Corridor is expected to significantly improve east-west connectivity in Kolkata by linking the southern parts of the city with the central business district. Once operational, the corridor will provide faster, safer and more sustainable public transport, helping reduce travel time and ease road congestion.

The successful breakthrough of TBM ‘Durga’ adds to a series of major milestones achieved by Kolkata Metro in recent weeks.

Earlier, Kolkata Metro successfully bridged the critical 62-metre viaduct gap at Chingrighata on the Kavi Subhash-Airport (Orange Line) corridor, removing a major construction hurdle and paving the way for faster progress towards completion of the line.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.