Bengal polls: Mob attacks central forces, 3 CAPF personnel injured in Birbhum | ‘People voting to protect their rights’: Mamata says high turnout backs TMC in Bengal | ‘Fear is being defeated’: PM Modi says high voter turnout signals BJP win in Bengal | Crude bomb attack in Murshidabad’s Nowda as violence hits Bengal polling | ‘Mamata Banerjee’s politics fuelled BJP growth in Bengal’: Rahul Gandhi | 'Will never forget’: Nation remembers Pahalgam victims as leaders vow strong fight against terror | 'India will never bow to any form of terror': PM Modi on Pahalgam terror attack anniversary | TCS Nashik case: No interim bail for Danish Shaikh in religious sentiments case | US woman alleges sexual assault at Karnataka homestay; owner among 2 arrested | ‘PM Modi is a terrorist’: Mallikarjun Kharge sparks row; BJP hits back
CPEC
Image: Pixabay

Chinese firm concerned over delay in launch of CPEC solar project in Pakistan

| @indiablooms | Oct 09, 2021, at 08:46 pm

Lahore: A Chinese state company has voiced its concerns over the inordinate delay in the launch and completion of the remaining 600-megawatt portion of the 900MW mega solar power project under the China-Pakistan Economic Corridor (CPEC) amid alleged issues related to the National Electric Power Regulatory Authority (Nepra) and the National Transmission and Despatch Company (NTDC), media reports said.

The firm, in its various communications to the CPEC Authority, Punjab government, Ministry of Energy (power division) and other authorities concerned, has sought immediate resolution of all issues enabling it to launch and complete the remaining part of the Quaid-i-Azam Solar Park in Bahawalpur, Dawn News reported.

“For the last couple of years, the Chinese company, which completed and commissioned 300MW of the 900MW project in 2016-17, has not worked further due to various official bottlenecks. The company has been running after government departments for this clean power generation project for the last couple of years, but to no avail,” explains an official source to Dawn News.

He claimed the remaining 600MW had not yet reached fruition because the issues related to tariff and interconnection study reports were yet to be resolved by Nepra and NTDC.

“Moreover, our re-affirmation of Grid Interconnection Study (GIS) and extension of IEE/NOC approvals and generation licences applications are pending with the NTDC (power planning wing), Nepra and Punjab Environment Protection Department,” the official added citing contents of a recent letter the company wrote to the quarters concerned.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.