Constitution ‘sacrosanct’ to PM Modi: Shashi Tharoor’s statement sets political chatter ablaze | A little piece of Greenland': Elon Musk takes a dig at Trump's Board of Peace at Davos | Over 5,000 killed during massive crackdown launched on Iranian protesters: Human rights body | 'Insult' in Kochi, silence in Delhi: Shashi Tharoor likely to skip key Congress meeting as party tensions surface | Outrage in America: ICE detains 5-year-old after he comes home from preschool | Top Maoist leader with ₹2 crore bounty among 16 eliminated in major Jharkhand encounter | Shockwave at Amazon: 14,000 jobs could be cut as early as next week! | Deloitte set to rename jobs of 1.8 lakh employees as AI forces big consulting reset | 'Bigger than tariffs': Ex-IMF economist Gita Gopinath flags pollution as India’s biggest economic threat | SC allows both Hindus and Muslims to pray at disputed Bhojshala in Madhya Pradesh on Basant Panchami
Dasu Project
Image: Twitter

Pakistan: Dasu Hydropower Project to miss completion deadline

| @indiablooms | Jan 07, 2023, at 03:37 am

Islamabad: The construction of the Dasu Hydropower Project (Stage-I), which has an installed capacity of 2,160 MW, will now miss the earlier competition deadline.

Power generation from the project is now expected to take place from 2026 end.

Project management, while giving a briefing to WAPDA Chairman Lt-Gen (Retd) Sajjad Ghani during his visit to Dasu Hydropower Project, said construction work was continuing simultaneously on 12 different sites, reports The Nation.

The critical diversion system will be completed in May 2023, while electricity generation from the project will commence by the end of 2026, said a statement issued here by WAPDA.

Due to Land acquisition issues, the COVID Pandemic, and terrorism incidents which are all beyond the control of Wapda, the expected COD of the Dasu Stage-I Hydropower Project (HPP) has been pushed till FY 2026-27, said WAPDA in its bulk supply tariff petition shared with National Electric Power Regulatory Authority (NEPRA), reports The Nation.

WAPDA had requested NEPRA to allow an extension in COD of the project till 2026-27.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.