November 05, 2024 15:57 (IST)
Follow us:
facebook-white sharing button
twitter-white sharing button
instagram-white sharing button
youtube-white sharing button
Union Minister HD Kumaraswamy booked for threatening cop probing into mining case | Supreme Court upholds validity of Uttar Pradesh Madrasa Education Act | Not all private properties are community resources that govt can take over: Supreme Court | Pakistan's Lahore has become world's most polluted city with an AQI of 1900 on Sunday | Indian Army 'successfully completes' patrolling to a key point in Ladakh's Depsang region
Chinese firm concerned over delay in launch of CPEC solar project in Pakistan
CPEC
Image: Pixabay

Chinese firm concerned over delay in launch of CPEC solar project in Pakistan

| @indiablooms | 09 Oct 2021, 03:16 pm

Lahore: A Chinese state company has voiced its concerns over the inordinate delay in the launch and completion of the remaining 600-megawatt portion of the 900MW mega solar power project under the China-Pakistan Economic Corridor (CPEC) amid alleged issues related to the National Electric Power Regulatory Authority (Nepra) and the National Transmission and Despatch Company (NTDC), media reports said.

The firm, in its various communications to the CPEC Authority, Punjab government, Ministry of Energy (power division) and other authorities concerned, has sought immediate resolution of all issues enabling it to launch and complete the remaining part of the Quaid-i-Azam Solar Park in Bahawalpur, Dawn News reported.

“For the last couple of years, the Chinese company, which completed and commissioned 300MW of the 900MW project in 2016-17, has not worked further due to various official bottlenecks. The company has been running after government departments for this clean power generation project for the last couple of years, but to no avail,” explains an official source to Dawn News.

He claimed the remaining 600MW had not yet reached fruition because the issues related to tariff and interconnection study reports were yet to be resolved by Nepra and NTDC.

“Moreover, our re-affirmation of Grid Interconnection Study (GIS) and extension of IEE/NOC approvals and generation licences applications are pending with the NTDC (power planning wing), Nepra and Punjab Environment Protection Department,” the official added citing contents of a recent letter the company wrote to the quarters concerned.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Images
Xi Jinping, Putin in Russia 22 Mar 2023, 02:56 pm
Related Videos