Ram Mandir Trust chief Champat Rai resigns as alleged donation siphoning row escalates | Ram Mandir fund row deepens: 8 arrested days after BJP called allegations 'false narrative' | 'Who tied the hands of CBI?': Calcutta HC on RG Kar case; victim's mother, now BJP MLA, says she is 'deeply disturbed' | Construction comes to a standstill at nearly 700 Kolkata projects after Taratala warehouse tragedy kills 15 | World Cup shocker! Ecuador stun Germany 2-1, storm into Round of 32 | Iran-US conflict: Cargo vessel hit near Strait of Hormuz, UN agency pauses evacuation operations | Amazon's massive India bet! Andy Jassy announces $48 billion investment after meeting PM Modi | Taratala warehouse collapse: Death toll climbs to 8, five arrested as SIT launches probe | Oil prices crash, IndiGo takes off! Aviation and fuel stocks emerge as biggest winners | Passport is a travel document, not conclusive proof of citizenship: MEA
Sunni Dam
Representational Image (Credit: Prateek Srivastava via Unsplash)

Cabinet grants investment approval for 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd

| @indiablooms | Jan 05, 2023, at 02:41 am

New Delhi/IBNS: The Cabinet Committee on Economic Affairs (CCAE) Wednesday approved the investment for the 382 MW Sunni Dam Hydro Electric Project in Himachal Pradesh by SJVN Ltd.

The estimated cost of the project is Rs. 2614.51 crore including Rs 13.80 crore as budgetary support from the government for the cost of enabling infrastructure.

Ex-post facto approval is given for cumulative expenditure incurred amounting to Rs 246 crore till January 2022.

The project cost includes hard costs amounting to Rs.2246.40 crore, Interest During Construction (IDC), and Financing Charges (FC) of Rs. 358.96 crore and 9.15 crore respectively.

The revised cost sanctions for cost variations due to quantity changes (including additions/ alterations/ extra items) and time overruns due to the developer is capped at 10 percent of the sanctioned cost.

The implementation of the project is expected to generate around 4000 direct and indirect employment during the peak construction of the project.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.