Bengal polls: Mob attacks central forces, 3 CAPF personnel injured in Birbhum | ‘People voting to protect their rights’: Mamata says high turnout backs TMC in Bengal | ‘Fear is being defeated’: PM Modi says high voter turnout signals BJP win in Bengal | Crude bomb attack in Murshidabad’s Nowda as violence hits Bengal polling | ‘Mamata Banerjee’s politics fuelled BJP growth in Bengal’: Rahul Gandhi | 'Will never forget’: Nation remembers Pahalgam victims as leaders vow strong fight against terror | 'India will never bow to any form of terror': PM Modi on Pahalgam terror attack anniversary | TCS Nashik case: No interim bail for Danish Shaikh in religious sentiments case | US woman alleges sexual assault at Karnataka homestay; owner among 2 arrested | ‘PM Modi is a terrorist’: Mallikarjun Kharge sparks row; BJP hits back
Nepal
Image: Pixabay

Kathmandu-Tarai expressway in Nepal to face further delay

| @indiablooms | Apr 02, 2021, at 10:43 pm

The completion of Nepal’s ambitious Kathmandu-Tarai expressway is likely to face further delay as the parliament’s Public Account Committee ordered the scrapping of the bidding process for the second phase of construction, reported Kathmandu Post.

 

The committee recommended the Nepali Army, which is executing the project, scrapping the bidding process as it found “serious procedural flaws” in the process.

“The committee’s study has found a serious breach of the Public Procurement Act and its regulation in the pre-qualification of construction companies for the second phase,” Roj Nath Pandey, secretary for the parliamentary committee, was quoted as saying by the Kathmandu Post.

“The committee has directed the scrapping of the entire process and starting a new one,” he said.

“We have fully adhered to the Public Procurement Act and its regulations. We can make further comments only after receiving the letter from the House committee,” Brigadier General Santosh Ballave Poudyal, the spokesperson for the Nepal Army, was quoted as saying by the Kathmandu Post.

The rules say that more than one company must be shortlisted in the pre-qualification phase while, in reality, the army had shortlisted just one company- a violation of the Public Procurement Act-2015.

Under the project, 86 bridges and 6.415 kilometers of tunnels are planned for construction.

The $1.8 billion project, scheduled to be completed by 2024, has already seen many delays leading to over 50 percent cost escalation so far.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.