Chinese firm seeks Rs 12.35bn dues from Pakistan for power project
Beijing: A leading state-owned Chinese firm has voiced its concern on delay of payments and asked Pakistan's Ministry of Energy (power division) to release Rs 12.35 billion as Transmission Service Payment (TSP) related to 660 kV Matiari-Lahore High Voltage Direct Current (HVDC) Transmission Line for September 2021 to February 2022, media reports said.
The China Electric Power Equipment and Technology Co Ltd (CET) / State Grid Corporation of China (SGCC) registered in Pakistan as Pak Matiari-Lahore Transmission Company Private Limited (PMLTC) has also quoted the Chinese government and the embassy as expressing their concern at the issue and asked the ministry to take up this issue on top priority, The Dawn reported.
In a recent letter to energy minister Hammad Azhar, the company explains that it has received the TSP for September to November 2021 and a partial payment (19.46 percent) for the month of December 2021.
It apprises the minster that in accordance with the Transmission Service Agreement (TSA), by beginning of March 2022, it should receive the TSP from September 2021 to February 2022, along with payment for adjustment of indexation, and the TSP for the pre-CoD (commercial operation date) period that remained pending at Rs 21.1 billion, whereas the payment it received so far is Rs 8.75 billion — 41.4 percent of the total amount it billed, the newspaper reported.
“We need to stress again that the total amount of invoices we billed NTDC is Rs 21.21bn, out of which, after receipt of Rs 8.75 billion, the unpaid amount is Rs 12.35bn,” reads the letter, seeking clearance of the amount not later than March 24 since the approval of foreign exchange conversion from the State Bank of Pakistan for making payment to lender takes time. It also desired to take the daily TSP to Rs 0.42 bn from Rs 0.05 to 0.15 bn to make it avert default under the facility agreement.
The company said: “Considering the difficulties we are facing, also both Chinese Government and the Chinese Embassy attach great importance to the payment issue of this CPEC flagship project, we humbly request your highest attention to immediately tackle this issue on top priority and instruct / coordinate with the parties concerned on urgent basis to make substantial effort for increasing day payment amount day by day to avoid default of the PMLTC’s obligations.”
The NTDC managing director told Dawn that no work related to checking, clearance of bills and sending to the Central Power Purchase Company (CPPA) was pending on the part of the project owner / client -- the NTDC. “This issue emerged before my appointment as MD. However, we always give priority to such payments. And we did,” he said.
He said the issue of payment to the PMLTC might exist on the part of the CPPA that is responsible for making such payments.
Support Our Journalism
We cannot do without you.. your contribution supports unbiased journalism
IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.