BJP reshuffles top organisation seven months after Nitin Nabin's elevation | West Bengal STF arrests suspected aide of ISI 'agent' Rana Rauf in Kolkata | ‘Very hopeful’: Indian envoy Dinesh Trivedi breaks silence on PM Tarique Rahman’s proposed India visit | Shehzad Poonawalla doubles down on BJP exit, urges party to accept resignation | Tarapith tragedy: Seven pilgrims killed as hotel goes up in flames before dawn | Bengal STF nabs suspected aide of ISI 'agent' Rana Rauf in Kolkata | After SC rebuke, BCI chief apologises to NALSAR students over enrolment freeze row | Independence Day: PM Modi’s big youth pitch— AI training, free coaching amid exam row and job concerns | ‘Shakti Ki Saptadhara’: Modi reveals 7 pillars to power India’s next leap in his I-Day speech from Red Fort | West Bengal STF arrests 3 more suspected Pakistani spies in Cooch Behar

Alstom T&D India commissions Rajasthan's first 765kV substation at Anta

| | Feb 03, 2015, at 06:51 am
New Delhi, Feb 2 (IBNS) : Alstom T&D India has successfully commissioned the Rajya Vidyut Prasaran Nigam Limited’s (RVPN) 765 kV substation in Anta.

Anta is Rajasthan’s first 765 kV substation, and the second largest with a total of twenty-six bays, ten 765 kV bays and sixteen 400 kV bays.

This substation will play a significant role in pooling and evacuating the power flow from the three major power plants in the state (Kalisindh, Kawai and Chhabra) to the national grid.

The turnkey project for Anta substation was awarded to Alstom T&D India in September 2011. 

The contract included installation of three banks of 3x500 MVA, 765/400 kV transformers, 765 kV reactors, other 765 kV equipment and civil works with a total order value of nearly €52 million (INR 4,212 million).

The Anta substation was set up by RVPN under the transmission system augmentation scheme to meet the growing energy demand in the state.

Currently, Rajasthan has an installed capacity of more than 5,000 MW, with over 3,000 MW still under construction.

Upon successful completion of this project, Rathin Basu, Country President, Alstom India & South Asia said, “The successful commissioning of the 765 kV Anta project is a major testimony in building Rajasthan’s HV and EHV grid. Despite challenging weather conditions, the Alstom and RVPN team commissioned the prestigious project in time to initiate power flow between Anta and Phagi substations. We look forward to building future HV and EHV substations to strengthen Rajasthan’s electrical grid, including potential large scale induction of renewable power.”


 

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.