Tragedy in the skies: Five IAF personnel killed in AN-32 crash in Assam | 'Ask probe officers whether I hid anything': Abhishek Banerjee hits back after pre-dawn police search | Police storm Abhishek Banerjee's house at 3 am tracking aide, Mamata arrives; seizure list says 'NIL' | Big boost for India's security: DRDO successfully tests advanced missile shield | Indian-origin man jailed for 34 years in UK over horrific kidnap, torture and rape case | Mamata's nightmare deepens! Saayoni Ghosh, Dev, Rachana Banerjee among 19 rebel MPs seeking TMC split | Trump claims US 'ended war with Iran', Tehran yet to confirm a deal | Heartbreak for Indian sports: Manu Bhaker's mentor Jaspal Rana passes away at 49 | Three Indian seafarers, missing after US strike on tanker near Oman, confirmed dead | 'Choose your side': TMC MP Kalyan Banerjee's ultimatum to Mamata in open revolt against Abhishek
Coal
Image Credit: Unsplash

Coal production from captive & commercial blocks jumps 58 pc in Apr-Aug FY23

| @indiablooms | Sep 07, 2022, at 02:52 am

New Delhi: Coal production during April-August (FY23) stood at 43.93 million ton, 57.74 percent higher than 27.85 million ton produced during the same period the previous year, the Ministry of Coal said Tuesday.

Coal production from coal blocks during April-August for fiscal 2022-23 has been reviewed by the Additional Secretary & Nominated Authority, of the Ministry of Coal, in the presence of project proponents.

Two mines auctioned in 2021 under commercial auction reforms have become operational and produced 2.36 million ton of coal in April-August, 2022-23.

At present, 37 captive and commercial mines are under production and it is expected that at least 11 more new mines will start production during the year.

This will significantly contribute to meeting coal demand in the country.

The ministry appreciated the efforts of coal block allottees in attaining such high growth and hoped that the target production of 141.78 million ton from these blocks during FY 2022-23 will be achieved.

At the same time, it was noted with concern that Parsa East & Kanta Basan coal block production has stopped and Parsa coal block production has not started. The continued stoppage may adversely impact the achievement of the target this year.

Further, during the review, project proponents shared the efforts made by them and the challenges faced. Ministry of Coal assured to extend all possible support in resolving the issues.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm