After SC rebuke, BCI chief apologises to NALSAR students over enrolment freeze row | Independence Day: PM Modi’s big youth pitch— AI training, free coaching amid exam row and job concerns | ‘Shakti Ki Saptadhara’: Modi reveals 7 pillars to power India’s next leap in his I-Day speech from Red Fort | West Bengal STF arrests 3 more suspected Pakistani spies in Cooch Behar | Bengal man arrested in Bengaluru over terror links, Afghanistan travel plan | Ajit Doval breaks silence on Operation Sindoor in Discovery’s explosive new docuseries | Rahul Gandhi's 'mock hug' taunt sparks row; Centre stresses 'mutual respect' with Italy | Delhi on high alert: Bomb threat to High Court, airport and multiple locations ahead of I-Day | ‘Who are they to interfere?’: CJI Surya Kant slams Bar Council of India over NALSAR students’ enrolment row | 'Shows how low Congress has sunk': BJP slams Rahul Gandhi over Modi foreign policy jibe

Essar Power Hazira Gujarat unit attains 100 per cent capacity utilisation

| | Mar 03, 2017, at 07:13 pm
Mumbai, Mar 3 (IBNS): Essar Power Hazira Ltd, a subsidiary of Essar Power Ltd, announced on Friday that its 2x135 MW power project in Hazira, Gujarat, has begun operating consistently at close to 100% capacity utilisation.

The company said it is a significant achievement because it comes close on the heels of the commissioning of the second unit, which occurred just three months ago.

It is also an indicator for the increased capacity utilisation of its captive client—Essar Steel’s 10 million tonne Hazira Steel Complex, the company said.

The plant can run on multiple fuels, like coal, corex fines and Corex gas, simultaneously. It can also utilize excess gases from the process units of steel making operations.

According to the company, the plant is also helping bring down Essar Steel’s power procurement cost, while lending flexibility to the steel-making process.

Essar Steel has increased its capacity utilisation from 30 per cent to 80 per cent over the past one year.

KVB Reddy, CEO, Essar Power, said, “The year is turning out to be an important one for Essar Power. Close to 80 per cent of Essar Power’s targeted capacity of 6,100 MW, which comprises both captive and IPP assets, have been made operational. In the last two years, increased coal availability, both from domestic and overseas suppliers, as well as the strong operational efficiencies harnessed by Essar Power’s world-class technical team have helped improve our performance significantly.”

In October 2016, Essar Power commissioned Unit 2 of Phase I (2X30 MW) of the 2x60 MW Paradip power project.

Earlier in May, the company restarted first unit of its 2x600 MW Mahan power project after a 19-month shutdown.

Essar Power Ltd is one of India's largest private sector power producers with over 20 years of operating track record.

It owns power plants in India and Canada  with a total planned generation capacity of 6,100 MW, of which 4,840 MW is operational.

Of the total operational capacity, 3,240 MW is coal-based, while 1,600 MW is gas-based.

The operating plants in India are at Mahan in Madhya Pradesh, Hazira, Salaya and Vadinar  in Gujarat and Paradeep in Orissa.

A 1,200 MW coal-based power plant in Tori, Jharkhand, is under development.


Image: Essar website

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.