India ready to offer possible assistance: PM Modi on Myanmar, Thailand earthquake | Magnitude 7.7 Earthquake hits Myanmar, strong tremors felt in Bangkok | 'Complete lawlessness': Suvendu Adhikari writes to Bengal Guv over Malda violence | 'You are a liar': Mamata Banerjee faces guests' ire over Singur, RG Kar, 'attack on Hindus' at London event | 3 cops killed, 2 terrorists shot dead during J&K's Kathua encounter: Report | Kolkata couple sues IVF centre for not revealing daughter's biological parents' identity, blames it for her death | 'India is not Dharamshala', Amit Shah says as Lok Sabha passes Immigration and Foreigners Bill 2025 | 'Now it's our turn': Vladimir Putin accepts Narendra Modi's invitation to visit India | Gold smuggling case: Kannada actor Ranya Rao’s bail plea rejected again | Congress workers clash with police in Odisha during protest against suspension of MLAs

Number of delayed infrastructure projects increase to 830

| @indiablooms | Sep 21, 2023, at 08:13 am

New Delhi: The number of delayed infrastructure projects valued at Rs 150 crore and higher in India has increased to 830 as of September 1, 2023, from 809 recorded on August 1, 2023, as per the August 2023 report from the Infrastructure and Project Monitoring Division (IPMD).

Out of the 1,762 projects under scrutiny, 830 are experiencing delays, 550 are progressing on the set schedule, and 43 projects are ahead of schedule.

The remaining 339 projects lack reported commissioning years or tentative gestation periods.

On average, these 830 delayed projects have an overrun of 36.96 months.

Within the delayed projects, 167 have reported additional delays compared to the previous month's completion date, with 59 being high-value mega projects worth Rs 1,000 crore or more.

Furthermore, among the 830 delayed projects, 194 have reported delays ranging from 1-12 months, 190 are facing delays between 13-24 months, 323 are experiencing delays spanning 35-60 months, and the remaining 123 are encountering delays exceeding 60 months.

The total cost overrun for the 1,762 infrastructure projects amounts to Rs 4,77,280.69 crore, which is 19 percent of the total cost.

"Total original cost of implementation of the 1,762 projects was Rs 25,01,400.62 crore and their anticipated completion cost is likely to be Rs 29,78,681.31 crore," the report said.

As of September 1, 2023, a total of Rs 15,57,188.10 crore has been expended on these 1,762 infrastructure projects, the report noted.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm
PM Modi on Budget 2024 Jul 23, 2024, at 09:30 pm
Close menu