Mamata's nightmare deepens! Saayoni Ghosh, Dev, Rachana Banerjee among 19 rebel MPs seeking TMC split | Trump claims US 'ended war with Iran', Tehran yet to confirm a deal | Heartbreak for Indian sports: Manu Bhaker's mentor Jaspal Rana passes away at 49 | Three Indian seafarers, missing after US strike on tanker near Oman, confirmed dead | 'Choose your side': TMC MP Kalyan Banerjee's ultimatum to Mamata in open revolt against Abhishek | Fresh trouble for Abhishek Banerjee! Calcutta HC orders TMC MP to appear before CID in forgery case by 6 pm today | 'No resignation, no retreat': Cockroach Janta Party takes paper leak protest nationwide | TCS goes all-in on AI! Partners with Anthropic, gives Claude access to 50,000 employees | Viral video outrage! Ola driver brutally assaults 70-year-old man over spitting row; arrested after Shinde's personal intervention | Mamata under pressure! Third Rajya Sabha MP Prakash Chik Baraik quits, hints at BJP move

Number of delayed infrastructure projects increase to 830

| @indiablooms | Sep 21, 2023, at 08:13 am

New Delhi: The number of delayed infrastructure projects valued at Rs 150 crore and higher in India has increased to 830 as of September 1, 2023, from 809 recorded on August 1, 2023, as per the August 2023 report from the Infrastructure and Project Monitoring Division (IPMD).

Out of the 1,762 projects under scrutiny, 830 are experiencing delays, 550 are progressing on the set schedule, and 43 projects are ahead of schedule.

The remaining 339 projects lack reported commissioning years or tentative gestation periods.

On average, these 830 delayed projects have an overrun of 36.96 months.

Within the delayed projects, 167 have reported additional delays compared to the previous month's completion date, with 59 being high-value mega projects worth Rs 1,000 crore or more.

Furthermore, among the 830 delayed projects, 194 have reported delays ranging from 1-12 months, 190 are facing delays between 13-24 months, 323 are experiencing delays spanning 35-60 months, and the remaining 123 are encountering delays exceeding 60 months.

The total cost overrun for the 1,762 infrastructure projects amounts to Rs 4,77,280.69 crore, which is 19 percent of the total cost.

"Total original cost of implementation of the 1,762 projects was Rs 25,01,400.62 crore and their anticipated completion cost is likely to be Rs 29,78,681.31 crore," the report said.

As of September 1, 2023, a total of Rs 15,57,188.10 crore has been expended on these 1,762 infrastructure projects, the report noted.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.
Related Videos
RBI announces repo rate cut Jun 06, 2025, at 10:51 am
FM Nirmala Sitharaman presents Budget 2025 Feb 01, 2025, at 03:45 pm
Nirmala Sitharaman on Budget 2024 Jul 23, 2024, at 09:30 pm