BJP reshuffles top organisation seven months after Nitin Nabin's elevation | West Bengal STF arrests suspected aide of ISI 'agent' Rana Rauf in Kolkata | ‘Very hopeful’: Indian envoy Dinesh Trivedi breaks silence on PM Tarique Rahman’s proposed India visit | Shehzad Poonawalla doubles down on BJP exit, urges party to accept resignation | Tarapith tragedy: Seven pilgrims killed as hotel goes up in flames before dawn | Bengal STF nabs suspected aide of ISI 'agent' Rana Rauf in Kolkata | After SC rebuke, BCI chief apologises to NALSAR students over enrolment freeze row | Independence Day: PM Modi’s big youth pitch— AI training, free coaching amid exam row and job concerns | ‘Shakti Ki Saptadhara’: Modi reveals 7 pillars to power India’s next leap in his I-Day speech from Red Fort | West Bengal STF arrests 3 more suspected Pakistani spies in Cooch Behar

ONGC Board approves KG basin block field development

| | Mar 28, 2016, at 08:29 pm
New Delhi/Mumbai, Mar 28 (IBNS) The Oil and Natural Gas Corporation Limited (ONGC) has informed that its Board, on Monday, has approved Field Development Plan (FDP) for development of Cluster 2 fields of Deep-water NELP Block KG-DWN-98/2.
KG-DWN-98/2 is part of the Krishna Godavari basin block. 
 
The development cost has been estimated at US$ 5076.37 million (approximately Rs 34,012 crores at USD 1 = INR 67).
 
Cluster 2 of the Block has been divided into two parts: Cluster 2A with an estimated in-place reserve of 94.26 million metric tons (MMt) of crude oil and 21.75 billion cubic metres (BCM) of associated gas and Cluster 2B with an estimated reserve of Free Gas of 51.98 BCM. 
 
ONGC envisages production at a peak oil rate of 77,305 barrel of oil per day (bopd) and 3.81 million metric standard cubic meter per day (MMSCMD) on associated gas through 15 producer wells along with 12 water injection wells with a peak water injection rate of 9400 m3/d from Clutser 2A oilfields.
 
Peak production rate of peak gas is envisaged at 12.75 MMSCMD  from eight wells of Cluster 2B free gas fields.
 
Total oil and gas production from Cluster 2 is estimated as 23.526 MMt and 50.706 BCM, respectively.
 
According to ONGC, the peak daily production rate from Cluster 2 is equivalent to 16.89 per cent and 27.60 per cent of its current production rate of crude oil and natural gas, respectively.
 
The company expects the first gas to be produced by June 209 and first oil by March 2020 with overall completion in June 2020.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.