Arvind Kejriwal, family ‘missing’ from Delhi voter list, claims Aam Aadmi Party | ‘No UPI above ₹2,000?’ Ghaziabad traders put up ‘cash only’ hoardings | Trump signs Russia sanctions bill: India faces fresh 100% tariff threat over Moscow oil | Caught using ChatGPT for exam answers, IIT Bombay student dies by suicide; students protest | Congress' Nandigram candidate arrested after Mamata's support amid TMC symbol row; Bengal bypoll gets chaotic | Gurugram murder shocker: Groom-to-be leaves sisters at Delhi restaurant to meet ex-colleague, found dead days later | Delhi horror: Teen allegedly gangraped, stabbed to death and dumped in field; dogs eat parts of body | TMC name, symbol frozen: EC tells rival factions to pick new identities ahead of Bengal bypolls | Married just 17 days ago: Hyderabad engineer mysteriously found dead at US home | ‘We will promote cash’: New UPI charge triggers trader backlash, Opposition protests
Jammu Roads

CEO ERA sets deadline for ongoing projects in Jammu  

| @indiablooms | Dec 18, 2020, at 10:21 pm

Srinagar: Chief Executive Officer, Jammu and Kashmir Economic Reconstruction Agency (JKERA) and Jammu TawiFlood Reconstruction Project (JTFRP), Dr. Syed Abid Rasheed Shah, conducted an inspection of ongoingSidhra Surinsar Road sub project being executed by JKERA under the World Bank funded Jhelum TawiFlood Recovery Project.

The Road starts from Sidhra Junction on Jammu-Srinagar Highway and isproposed to be upgraded upto km 19th of Sidhra-Surinsar Road.

The completion of this road will augment the road infrastructure to the tourist circuit of Sidhra-SurinsarMansar. It will also connect the important religious destinations of Utterbehni and Purmandal.During the inspection the CEO passed strict instructions for immediately speeding of the work andcompleting the project in the next 7 months.

Major civil works of road consist of improvement of roadgeometrics and widening of blind curves/black spots.

The CEO directed the engineering staff andcontractor to ensure that quality of the civil works is maintained as per best standards.

Engineering staff gave a detailed presentation to the CEO and apprised that the major component ofaround 60% comprises macadamisation/bituminization which will be done after the first week of March2021.The CEO directed the contractor to immediately increase the manpower and machinery deployed toensure that the project is completed well within time.

On the spot directions were issued to theEngineering staff for strict weekly monitoring of progress.Dr. Abid was accompanied by Nand Kishore Gupta Project Manager, Rajinder Kumar Sharma DeputyProject Manager and other Engineering Staff of JTFRP and consultancies along with the representativesof contractors.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.