Arvind Kejriwal, family ‘missing’ from Delhi voter list, claims Aam Aadmi Party | ‘No UPI above ₹2,000?’ Ghaziabad traders put up ‘cash only’ hoardings | Trump signs Russia sanctions bill: India faces fresh 100% tariff threat over Moscow oil | Caught using ChatGPT for exam answers, IIT Bombay student dies by suicide; students protest | Congress' Nandigram candidate arrested after Mamata's support amid TMC symbol row; Bengal bypoll gets chaotic | Gurugram murder shocker: Groom-to-be leaves sisters at Delhi restaurant to meet ex-colleague, found dead days later | Delhi horror: Teen allegedly gangraped, stabbed to death and dumped in field; dogs eat parts of body | TMC name, symbol frozen: EC tells rival factions to pick new identities ahead of Bengal bypolls | Married just 17 days ago: Hyderabad engineer mysteriously found dead at US home | ‘We will promote cash’: New UPI charge triggers trader backlash, Opposition protests
Kashmir
Image Credit: File photo of CS J&K, Arun Kumar MehtaDIPR

Kashmir Chief Secretary for physical verification of works, projects under District Capex

| @indiablooms | Jul 18, 2021, at 04:18 am

 Jammu: J&K Finance department has scheduled two weeks from August 2 to 15 as “pace setting weeks” for physical verification of the works or projects under District Capital

Expenditure (Capex) Financial Commissioner, Finance department, A K Mehta, who is also the Chief Secretary of J&K, has issued this direction to “expedite 100 percent physical verification of the works or projects of District Capex completed during the Financial Year 2020-21.

In this connection, Mehta, in a Finance department circular, has enjoined upon the Regional Directors Kashmir and Jammu and all the District Statistical Evaluation Officers (DSEOs) of UT of J&K to ensure that two works or projects should be physically verified per district per day during these two weeks.

Thus, around 250 works or projects at divisional level and around 500 works or projects in the UT of J&K will be physically verified in two weeks. Works will be taken up from an e-compendium of 1676 completed projects during 2020-21 available on the official website of the Finance department.

“All DSEOs shall furnish the discrepancies, so found during Pace setting weeks to all concerned executing agencies vis-a-vis furnishing the Physical Verification Reports to the Regional Directors by August 23, 2021. DSEOs shall further submit the action taken by the Executing agencies to Regional Directors by August 30, 2021 and the same shall be furnished by Regional Directors to the Finance Department by September 5, 2021,” Mehta has directed while specifying the time lines.

He has instructed the Regional Directors Kashmir and Jammu to furnish the work-wise discrepancies found during Pace setting weeks as per the format to the Finance department by August 30, 2021.

“Timelines shall be adhered to strictly. Any deviation to the instructions shall be the personal responsibility of the concerned officer,” Mehta has warned.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.