Kanpur plane crash: Training aircraft crashes near Ganges, two pilots killed | Big IT boost for Bengal: LTM opens global delivery & AI centre in Kolkata's New Town | 21-year-old Delhi model found stabbed at Delhi home, gym trainer accused of killing her | ‘Who is stopping her from wearing what she wants?’: Kangana Ranaut hits back at Kriti Sanon over Raksha Bandhan ad | 300 Indians missing in Nepal flash floods, 160 dead: Foreign Minister reveals grim toll | Supreme Court directs Tarun Tejpal to surrender within two weeks | Supreme Court notice to 20 rebel TMC MPs in disqualification plea | ‘Reservation for poor, not caste’: Stir at Delhi’s Jantar Mantar | Dalit woman 'gangrape-murder' shocker in Karnataka: 4 arrested after body found in well | India dismisses Pakistan's 'frustration' over US envoy's J&K remark
Jhelum River

Kashmir's Jhelum river carrying capacity enhanced by 25 percent from 2014

| @indiablooms | Oct 13, 2021, at 10:48 pm

Srinagar/IBNS: To prevent 2014-like floods in the Kashmir division, the carrying capacity of the river Jhelum has been enhanced by 25 percent by dredging of the river and its flood spill channels.

The 2014 devastating floods in Srinagar and its adjoining areas wreaked havoc and caused an estimated one lakh crore loss to the public and private infrastructure.

Subsequently, the Centre announced a 'Plan for Comprehensive flood management of River Jhelum and its tributaries’.

The Flood Management Plan was divided into two parts- Phase 1 and Phase 2- and so far 98 percent progress has been achieved on phase 1, while for phase 2 the J&K administration is awaiting release for funds from the Centre.

Chief Engineer of Irrigation and Flood Control Naresh Kumar said, "Carrying capacity of river Jhelum has been enhanced by 25 percent from what it was in 2014. We have done spot dredging of flood channels where the need was felt to do so.

He said, "For Phase 2 part A, investment clearance for Rs 1,623 crore has been already cleared, now we are awaiting release of funds as the Department of Water Resources have informed that funds will be released only  after they will put this project in their five year plan for 2022-26."

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.