Bengal CM Suvendu Adhikari backs move to stop entry to Bankra Mosque inside Kolkata airport operational area | Big win for Vijay government! Supreme Court stays Madras HC's cow slaughter ban in Tamil Nadu | Badrinath Temple donation theft case: Key accused Pramod Nautiyal arrested in major breakthrough | 'Citizenship must be decided fairly': Supreme Court quashes Gauhati HC order declaring 27 as foreigners | 'Highway blocked, stones pelted, cops injured': BJP faces open revolt in Madhya Pradesh over Narottam Mishra ticket snub | Two Kolkata Police DCPs suspended over alleged remarks against Bengal CM Suvendu Adhikari | Bail to Bloodbath: Telangana man allegedly kills wife, kids and teen who accused him of sexual harassment | Prakash Raj gets bail in multiple voter registration case linked to 2019 polls | ED raids Shekhar Suman associate's premises in FEMA case; phone allegedly thrown from 13th floor | 'Candidate fled': Prashant Kishor jibes BJP over Bankipur nominee change
North East

Railway connectivity towards NE gets a boost with commissioning of double line

| @indiablooms | Jul 03, 2021, at 06:43 pm

Guwahati/IBNS: CRS (Commissioner of Railway Safety) has accorded sanction for opening of Jalpaipuri Road - Y Leg section (one block section of 5 km) and Betgara - Kolaigram section (23 km in 3 block sections) double line falling on the Rajdhani route and the most busy route of N.F. Railway connecting Guwahati to rest of India.

In both these sections, double lines have been commissioned along with Railway Electrification. Completion of these doubling sections will help operation of more freight traffic to & from Northeast region.

The entire work is completed during the Covid pandemic situation by observing necessary safety protocols by the Northeast Frontier Railway.

An official of N.F. Railway said that, Jalpaiguri Road - Y Leg section was the only super critical work left to be completed in N.F. Railway.

“This section has an important bridge of 970 mt length (20 spans) on the river Teesta. This section was a bottleneck as double lines on either side of this block section already existed. Doubling on either side of Y Leg is important as this junction provides alternate route between New Jalpaiguri and New Coochbehar. Betgara - Kolaigram section is a part of New Mainaguri - Gumanihat doubling project which is a critical work of N.F. Railway,” the official said.

He further said that, this doubling being on the busiest route of N.F. Railways give a lot of advantage in increasing the line capacity of this section. A permanent speed restriction of 90 km per hour had also been removed in the process of this doubling. A three lane road over bridge of 60 m span with bow string girders has been constructed on National Highway 31-D which is a first on this Railway.

It is expected that with the completion of these two critical sections, trains to and from Northeast will be able to move at a much faster speed and thereby benefiting travelling public.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.