No third party involved: India govt sources refute China’s Operation Sindoor ceasefire claim | Amit Shah blasts TMC over border fencing; Mamata fires back on Pahalgam and Delhi blast | 'A profound loss for Bangladesh politics': Sheikh Hasina mourns Khaleda Zia’s death | PM Modi mourns Khaleda Zia’s death, hails her role in India-Bangladesh ties | Bangladesh’s first female Prime Minister Khaleda Zia passes away at 80 | India rejects Pakistan’s Christmas vandalism remarks, cites its ‘abysmal’ minority record | Minority under fire: Hindu houses torched in Bangladesh village | Supreme Court puts Aravalli redefinition on hold amid uproar, awaits new expert committee | Supreme Court strikes! Kuldeep Sengar’s bail in Unnao case suspended amid public outcry | From bitter split to big reunion! Pawars join hands again for high-stakes civic battle
North East

Railway connectivity towards NE gets a boost with commissioning of double line

| @indiablooms | Jul 03, 2021, at 06:43 pm

Guwahati/IBNS: CRS (Commissioner of Railway Safety) has accorded sanction for opening of Jalpaipuri Road - Y Leg section (one block section of 5 km) and Betgara - Kolaigram section (23 km in 3 block sections) double line falling on the Rajdhani route and the most busy route of N.F. Railway connecting Guwahati to rest of India.

In both these sections, double lines have been commissioned along with Railway Electrification. Completion of these doubling sections will help operation of more freight traffic to & from Northeast region.

The entire work is completed during the Covid pandemic situation by observing necessary safety protocols by the Northeast Frontier Railway.

An official of N.F. Railway said that, Jalpaiguri Road - Y Leg section was the only super critical work left to be completed in N.F. Railway.

“This section has an important bridge of 970 mt length (20 spans) on the river Teesta. This section was a bottleneck as double lines on either side of this block section already existed. Doubling on either side of Y Leg is important as this junction provides alternate route between New Jalpaiguri and New Coochbehar. Betgara - Kolaigram section is a part of New Mainaguri - Gumanihat doubling project which is a critical work of N.F. Railway,” the official said.

He further said that, this doubling being on the busiest route of N.F. Railways give a lot of advantage in increasing the line capacity of this section. A permanent speed restriction of 90 km per hour had also been removed in the process of this doubling. A three lane road over bridge of 60 m span with bow string girders has been constructed on National Highway 31-D which is a first on this Railway.

It is expected that with the completion of these two critical sections, trains to and from Northeast will be able to move at a much faster speed and thereby benefiting travelling public.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.