‘Restriction, not complete closure’: Supreme Court questions Delhi shutdown ahead of CJP protest | 'Unwarranted': India hits back at JD Vance over ‘indentured servants’ remark amid US Green Card crackdown | US targets Microsoft, Infosys, Tata in green card crackdown | ‘Bold and inventive’: Canadian poet Anne Carson wins 2026 Nobel Prize in Literature | ‘Attempt to destabilise world’s largest democracy’: 42 retired judges rally behind Gyanesh Kumar over ‘vote chori’ row | ‘Vote chor, gaddi chod’: Dhruv Rathee, Prakash Raj join Bengaluru protest against Gyanesh Kumar | India condemns Houthi attacks on Saudi airports, calls targeting of civilian infrastructure unacceptable | Dalal Street bloodbath: Investors lose Rs. 8 lakh crore as Sensex crashes over 1,000 points | Amazon layoffs hit India, US and UK: Fresh job cuts rock e-commerce giant amid festive shopping season | Bollywood mourns Nana Patekar: Anupam Kher, Akshay Kumar, Jr NTR, Suniel Shetty pay emotional tributes
Subansiri Hydropower Project
Subansiri Hydropower Project begins wet commissioning. Photo: NHPC Limited/Facebook

Subansiri Hydropower Project begins wet commissioning, India’s largest hydro project nears power generation

| @indiablooms | Oct 26, 2025, at 02:36 pm

India’s largest hydropower project, the 2,000 MW Subansiri Lower Hydroelectric Project near the Arunachal Pradesh–Assam border, has begun wet commissioning of its first unit, officials said.

NHPC Limited announced that the 250 MW Unit–I of the project underwent a test run on October 24, 2025. Wet commissioning involves running the turbine with water to check operational parameters without generating electricity. The process is expected to last four to five days, officials said.

The project comprises eight units of 250 MW each. NHPC said four of the units are ready for test runs, and the next step will involve synchronising at least two units with the national grid to start power generation.

In a statement issued on Facebook, NHPC said: "In a landmark moment for India’s hydropower sector, Wet Commissioning of Unit–I (250 MW) of NHPC’s 2000 MW Subansiri Lower Hydroelectric Project commenced on 24.10.2025 with successful mechanical run of the machine, marking the beginning of commissioning of the first unit of the nation’s largest hydropower project. Standing tall as NHPC’s largest-ever unit capacity, this milestone celebrates engineering mastery, teamwork and a shared vision of powering a greener tomorrow."

With Unit–I successfully wet-commissioned, synchronization with the national grid is expected soon, followed by three more 250 MW units this year, adding 1,000 MW of electricity.

Upon completion, the Subansiri Lower HEP (8×250 MW) will be India’s largest hydroelectric power station, significantly contributing to the nation’s energy security and sustainable development.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.