August 16, 2026 12:49 pm (IST)
Follow us:
facebook-white sharing button
twitter-white sharing button
instagram-white sharing button
youtube-white sharing button
After SC rebuke, BCI chief apologises to NALSAR students over enrolment freeze row | Independence Day: PM Modi’s big youth pitch— AI training, free coaching amid exam row and job concerns | ‘Shakti Ki Saptadhara’: Modi reveals 7 pillars to power India’s next leap in his I-Day speech from Red Fort | West Bengal STF arrests 3 more suspected Pakistani spies in Cooch Behar | Bengal man arrested in Bengaluru over terror links, Afghanistan travel plan | Ajit Doval breaks silence on Operation Sindoor in Discovery’s explosive new docuseries | Rahul Gandhi's 'mock hug' taunt sparks row; Centre stresses 'mutual respect' with Italy | Delhi on high alert: Bomb threat to High Court, airport and multiple locations ahead of I-Day | ‘Who are they to interfere?’: CJI Surya Kant slams Bar Council of India over NALSAR students’ enrolment row | 'Shows how low Congress has sunk': BJP slams Rahul Gandhi over Modi foreign policy jibe
Pakistan
Image: Pixabay

Pakistan: Russian gas line project stands in jeopardy

| @indiablooms | Jul 09, 2021, at 12:43 am

Islamabad:  Pakistan Stream Gas Pipeline (PSGP), also known as North-South Gas Pipeline, is finding a tough situation as the Petroleum Division has started finalizing an alternate gas pipeline project by mid-July, media reports said.

The development is also putting the ties with Russia, which have improved a lot in recent years, in jeopardy.

Pakistan and the Russian Federation signed the amended Inter-Governmental Agreement (IGA) on May 28, 2021 in Moscow on Pakistan Stream Gas Pipeline Project (PSGP), now both the countries have to sign the share-holders Agreement (SHA) within 60 days from the signing of the protocol scheduled for July 27, 2021, reports The News International.

Moscow sent a letter to Islamabad on June 07, informing that a Russian delegation wants to visit Pakistan from June 22 for talks on the Heads of Terms and Shareholders Agreement with participation of nominated entities ISGS and “PAKSTREAM” and competent authorities from the Pakistani side. But there was no immediate response from the Pakistan side, the newspaper reported.

The problems began immediately after the signing of the amended IGA.

As many as 27 days after the agreement was signed, CCOE (Cabinet Committee on Energy) that met on June 24 asked the Petroleum Division to finalize an alternate gas pipeline project by mid-July 2021, arguing there are massive negative consequences of the delay in the implementation of PSGP and the deadline set by the Supreme Court has already been missed with no imminent possibility of start of work.

“Therefore, an alternate plan needs to be finalized as soon as possible but not later than mid-July 2021,” says the decision of CCOE, the newspaper reported.

Support Our Journalism

We cannot do without you.. your contribution supports unbiased journalism

IBNS is not driven by any ism- not wokeism, not racism, not skewed secularism, not hyper right-wing or left liberal ideals, nor by any hardline religious beliefs or hyper nationalism. We want to serve you good old objective news, as they are. We do not judge or preach. We let people decide for themselves. We only try to present factual and well-sourced news.

Support objective journalism for a small contribution.